Welcome to our Free CSCS Mock Test For Managers and Professionals. If you are working on a construction site in a managerial role, you will have to take this test to get hold of your card, for example, the CSCS Black Managers card and the Academically or Professionally Qualified person cards.

We have included a wide range of questions in this test, there are over 450 questions selected at random to provide you with a 50-question managers CSCS card mock test. So please take this a few times so you can view the different questions and answers.

The managers and professionals CSCS is the same length as the CSCS test for Operatives, it is 45 minutes long, but you will need to score at least 46 out of 50 to pass the exam. There is a larger bank of questions to revise and 3 extra categories to learn:

CSCS Mock Test for Managers and Professionals

If you want to work on a construction site and gain your black card, then you will need to have a good understanding of these questions as you will be asked questions on them in the real exam.

In this mock test, we have provided the latest 50 questions you might be asked when sitting your real CSCS Test. In order to pass your managers and professionals test, you will need to score at least 46 out of 50 correct answers in 45 minutes.

1. How can noise affect someone’s health? Give two answers.
A.
B.
C.
D.
E.
2. A work crew is using an insulated pick to break up a surface. What two hazards should they be aware of?
A.
B.
C.
D.
E.
3. If the airbag being used for fall arrest has a controlled leak rate, what requirement must the inflation pump meet?
A.
B.
C.
D.
4. Who must be legally notified of a death, specified injury, dangerous occurrence or over 7-day injury on a site?
A.
B.
C.
D.
5. When should you take precautions to prevent people, materials or equipment from falling into an excavation?
A.
B.
C.
D.
6. Which is the most important reason for keeping a working area on a construction site clean and tidy?
A.
B.
C.
D.
7. When assessing pollution risk, before starting works on a construction site, which of the following is bad practice?
A.
B.
C.
D.
8. When should eye protection be worn?
A.
B.
C.
D.
9. When can a mobile plant operator let people ride in, or on, the machine?
A.
B.
C.
D.
10. If a person is going to be working on a mobile tower but will not be erecting, altering or dismantling it, what training should they have?
A.
B.
C.
D.
11. What colour are emergency and safe condition signs, such as fire exit and first aid points?
A.
B.
C.
D.
12. What is a near miss?
A.
B.
C.
D.
13. What is the first question to ask if work may need to be carried out in a confined space?
A.
B.
C.
D.
14. The standards of health and safety on a project site have noticeably declined. What is the first thing you should do to find out about the contractors attitude two health and safety?
A.
B.
C.
D.
15. For safety reasons how should you store or use liquefied petroleum gas (LPG) cylinders used for heating the site cabin?
A.
B.
C.
D.
16. What illness might a worker develop if they breathe in asbestos dust?
A.
B.
C.
D.
17. A plant refuelling point is to be set up on a new site. Which of the following is the preferred method of fuel transfer?
A.
B.
C.
D.
18. What does wearing hearing protection do?
A.
B.
C.
D.
19. Who has a role to play in promoting fairness, inclusion and respect in the construction industry?
A.
B.
C.
D.
20. What should you do if a worker tells you that a guard is missing from a power tool?
A.
B.
C.
D.
21. When observing the use of oxyacetylene-welding equipment, how should the bottles be positioned?
A.
B.
C.
D.
22. Where should you find out the number of people who may be carried in a passenger hoist on site?
A.
B.
C.
D.
23. You are about to carry out refurbishment works on a structure which was constructed after the introduction of the Construction (Design and Management) Regulations 2015. In which of the following areas are you most likely to find relevant information for the initial development of pre-construction information?
A.
B.
C.
D.
24. Disposable masks have filtering facepiece ratings of FFP1, FFP2 and FFP3. Which offers the greater protection?
A.
B.
C.
D.
25. Which two of the following factors must be considered when providing first-aid facilities on site?
A.
B.
C.
D.
E.
26. You when leaving a site you have been visiting you noticed that a contractor is working in an unsafe manner. What should you do?
A.
B.
C.
D.
27. Why is it important for all workers to attend site induction?
A.
B.
C.
D.
28. What should you do if you see this label on a container or packaging? Ghs Health Hazard
A.
B.
C.
D.
29. You become aware that an active bird’s nest has been destroyed on your site. Which of the following is a possible outcome?
A.
B.
C.
D.
30. Why is methane gas dangerous in confined spaces? Give two reasons.
A.
B.
C.
D.
E.
31. What is the correct procedure for using a tower crane to offload a lorry?
A.
B.
C.
D.
32. In accordance with the Construction (Design and Management) Regulations 2015, under normal circumstances, what written information must a principal contractor make available to workers or their representatives upon request?
A.
B.
C.
D.
33. Why may a young person be more at risk of having accidents?
A.
B.
C.
D.
34. You are planning a site’s power set-up. Which of the following is the most energy efficient?
A.
B.
C.
D.
35. What happens if probation notice is issued by a health and safety executive inspector or local authority?
A.
B.
C.
D.
36. When is the only time that you do not need to wear head protection on site?
A.
B.
C.
D.
37. What does this sign mean? E012 Safety Shower
A.
B.
C.
D.
38. How should workers find out what to do if they are injured on site?
A.
B.
C.
D.
39. If employees have to work outdoors in bad weather, why should you supply them with waterproof clothing?
A.
B.
C.
D.
40. What should you do if your personal protective equipment (PPE) gets damaged?
A.
B.
C.
D.
41. If someone is in contact with a live cable, what should you do first?
A.
B.
C.
D.
42. What is the best way to make sure that a ladder is secure and won’t slip?
A.
B.
C.
D.
43. How should you be informed about emergency assembly points?
A.
B.
C.
D.
44. What is the legal duty of the site manager when an invasive species of plant, such as Japanese knotweed, is discovered on site?
A.
B.
C.
D.
45. After gaining access to the platform of a mobile tower, what is the first thing you should do?
A.
B.
C.
D.
46. You have to use a new substance for the first time and need to carry out a COSHH assessment. What are the two main things you will need?
A.
B.
C.
D.
E.
47. What duty of care documentation should you use for hazardous waste leaving your site?
A.
B.
C.
D.
48. If someone collapses with stomach pain and there is no first aider on site, what should you do first?
A.
B.
C.
D.
49. Which of the following does not ensure good health and safety standards on a demolition project?
A.
B.
C.
D.
50. What sort of rest area should be provided for workers on site?
A.
B.
C.
D.

 

Whats invloved in the CSCS Test for Managers (MAP)

The CSCS test for managers, also known as the Management and Professional (MAP) Test , is designed to assess an individual's knowledge and understanding of health and safety in the construction industry. The test covers a range of topics, including:

  • General health and safety principles
  • Risk assessment and control measures
  • Fire safety
  • Manual handling
  • Personal protective equipment
  • Working at heights
  • Electrical safety
  • Environmental protection
  • First aid
  • Welfare facilities and provisions
  • Health and safety law

The CSCS test for managers consists of 50 multiple-choice questions, and applicants must answer at least 47 of them correctly to pass the test. The test is taken online, and applicants have 45 minutes to complete it. A CSCS card will be issued to individuals who pass the test, which allows them to work as managers in the construction industry.

Click on a star to rate it!

Average rating 4.7 / 5. 145

No votes so far! Be the first to rate this post.

Why Not Try Out These Tests Next

Leave a Reply to Darren Evans Cancel reply

Your email address will not be published. Required fields are marked *

64 comments on “CSCS Mock Test For Managers and Professionals”

  1. I checked with the official app. The answer to this question is wrong:
    Which two of these activities are likely to need a hot-work permit?

    The correct answer shouldn't include:
    "Refuelling a diesel dump truck"

    1. Hi Dyl

      Thanks for the heads up, you are completely right! Not sure how this got mixed up on the results, but thank you for letting us know. This has now been corrected

  2. Excellent mock test. It helped to emphasize the importance of reading the question

  3. Great help. I want to donate towards this useful service but won't use email banking. If there's any other way to contribute I will certainly.

  4. What a great site. Really helpful in letting you gauge your knowledge level. Especially nice is that you can see where you have gone wrong and learn from mistakes

  5. Shows the importance of reading the questions fully, before answering, and not rushing to finish.

  6. These mock test are a real help, when sitting the test, you are not made aware of why you got a question wrong this is most frustrating not to under stand your error.

  7. it is really helpful
    most of these question are in actual exam
    Thank you

  8. Very good, my revision was based on the 2016 CITB booklet and all the areas of the mock were covered within it. I advise anyone to obtain the latest version of the booklet before attempting this exam.

  9. Q28 28. A. Which of these statements about personal protective equipment (PPE) is not true?
    A. Workers must use it as instructed
    B. Workers must report any damage or loss to their manager
    C. Workers must store it correctly when they are not using it
    D. Workers must pay for any damage or loss
    I answered D and it says I got it wrong?

ConstructionExam.co.uk is not associated or part of any scheme
or organisation such as the CSCS, CPCS or CITB. The only intention of this website is to
provide information about these schemes and their assessments.
? linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram